"Utilization is not great," Rob Perlman said in June 2016. At the time he was president and chief operating officer of Steamboat Ski and Resort Corp., and he was explaining why the Bashor Bowl halfpipe had almost been cut. Steamboat Pilot & Today reported then that the 18-foot pipe could use as much as 15 percent of the resort's annual snowmaking. Grooming it also took one of the resort's two winch cats for much of the night, four or five nights a week. The decision to bring it back for 2016-17 came only a week before that story ran. Under a one-year arrangement, the Steamboat Springs Winter Sports Club agreed to share part of the cost.
Ten winters later, the pipe is getting its biggest rebuild in decades. The fix is dirt. Since late August, crews have been hauling excavation from The Stockman, the nine-story project going up at the ski area base, into Bashor Bowl to build up the base of Maverick's Halfpipe. The excavation was expected to produce more than 40,000 cubic yards of dirt, and on Oct. 23 Steamboat Pilot & Today reported that the pipe was nearing completion. The Bashor pipe has always faced two limits: the slope under it wasn't steep enough, and building it took too much snow. The new design goes after both, and the change could affect more than the riders who drop in.
Bashor had the location and lacked the slope
People who rode Bashor in the early 2000s remember how ambitious the pipe once was. Steamboat built 12-foot pipes through the 1990s, moved to 15-foot walls in 2001, and for a while marketed a pipe close to 700 feet long as the longest in North America. Riders told the resort it was too long, so it was shortened. In 2006 the walls went up to 18 feet.
After that the resort stopped upgrading. Before the 2010 Olympics, the competition standard moved to 22-foot walls, and Steamboat kept its 18-foot pipe. Jim Schneider, then the resort's vice president of skier services, gave the 2016 Pilot several reasons. He put the equipment cost of going from 18 to 22 feet at $200,000 to $400,000. He also said Bashor Bowl wasn't steep enough to hold a bigger pipe. The same story noted that Steamboat's elite snowboarders were training elsewhere in winter to be closer to world-class pipes.
Club coaches and athletes liked Bashor itself. In the same story, Tori Koski, then director of the SSWSC snowboard program, said the bowl sits high enough to avoid the worst spring slush. She also said its angle to the sun keeps one wall from melting faster than the other. The Bashor chair runs the length of the bowl, so riders can lap the pipe quickly. In a Steamboat Magazine profile before the Beijing Olympics, Taylor Gold, who trained with the club, described what that meant for him:
"The Bashor chair at the Steamboat Ski Area also offered really fast laps in the pipe, so I was able to get tons of reps in a short amount of time."
That left one problem to solve. The location worked, but the slope under the pipe did not.
Twenty-two feet, then the pitch
The walls changed first. The resort's 2025/26 press kit says the terrain park crew raised the Mavericks pipe from 18 to 22 feet in winter 2023/24. That gave Steamboat competition-height walls on the same slope Schneider had called too flat.
According to the Pilot's Oct. 23 story, slope maintenance director Jake Ingle said a 22-foot pipe needs a grade of at least 17 degrees. FREESKIER reported that last season's pipe was 17 degrees, so it was right at that minimum. Getting it there took a large volume of snow.
The Stockman's excavation offered a different approach. Native Excavating, the Steamboat company that won the bid to haul the dirt, asked Ingle whether the resort could use it. Ingle has built superpipes and boardercross venues for the U.S. Ski and Snowboard team. He has also worked on Olympic qualifier and Grand Prix venues at Mammoth, Park City, Copper and Breckenridge, and he built the pipe for the 2018 PyeongChang Olympics. The crew reviewed twelve designs and picked one based on PyeongChang. Alterra's development team, Steamboat Resort and Marquee Development, which is building The Stockman, all worked on the project.
| Last season | New build | |
|---|---|---|
| Wall height | 22 feet | 22 feet |
| Pitch | 17 degrees | 18.5 degrees |
| Length | 400 feet | About 500 to 550 feet |
| Snow to build | About 1.4 million cubic feet | About 750,000 cubic feet |
The old dimensions come from FREESKIER and the resort press kit. The sources disagree on the new length. FREESKIER cites the resort at roughly 500 feet, and the Pilot reported around 550. The snow figures are Ingle's, from the Pilot. FREESKIER also reported that the dirt work leaves room for a pipe up to 600 feet long if Steamboat ever wants one for a competition.
The shape is permanent. The city requires the slope to revegetate, so the inside walls of the dirt form are set at a 2-to-1 angle. In PyeongChang they were 1-to-1. Ingle calls the gentler inside slope a "catcher's mitt" for snow, which gives his crew room to shape the walls each winter. He told the Pilot the work went to Bashor partly because the bowl is on resort property, which made city permitting easier.
Less snow in the pipe means more snow for other terrain
The figure behind the 2016 debate was the 15 percent share of snowmaking. The new design goes straight at it. The resort's Oct. 22 announcement, published by Steamboat Radio, says the raised base should cut the snowmaking and natural snow needed to build the pipe by 40 to 60 percent. Ingle's numbers fall within that range: about 750,000 cubic feet of snow, down from 1.4 million, which is a little under half.
Ingle told the Pilot that this snow goes to other parts of the mountain. "For the next 20 years we are going to be able to build this halfpipe using half the snowmaking," he said. "We can move on to other areas of the mountain more quickly to use our snowmaking capacity." So people who never ride the pipe could still benefit if snowmaking crews finish Bashor sooner and move on to other runs.
When the pipe might open
For many local riders, the opening date matters most. The pipe has usually opened late. In 2016 the Pilot reported that the resort aimed for late December, before Christmas if possible, but that New Year's Day was often more realistic. In December 2003, a haul-cat breakdown pushed a planned Saturday opening back by at least a day. FREESKIER describes skiers waiting until about halfway through the season.
The resort says the new pipe should open "earlier in the season." It has not published a date. Here is the early-season calendar so far:
- Nov. 21: Steamboat Resort's opening day.
- Dec. 1: On-snow training begins for the SSWSC Snowboard Senior Team, which trains advanced slopestyle and halfpipe and holds sessions at Steamboat Resort. Its listed season runs through April 9.
- Late December to New Year's: The traditional target for opening the old pipe, and the date the new one is meant to beat.
The Bashor chair keeps laps short. Ingle estimates a lap through the new pipe at about two minutes and 30 seconds. Skiers and riders working up to it can use the beginner Mini-Mavs pipe in the Lil' Rodeo park, and Rabbit Ears is the intermediate park.
Built for local riders first
Arielle Gold won Olympic bronze in 2018, and Taylor Gold rode halfpipe for the U.S. in Beijing in 2022. A Pilot profile of Arielle Gold notes that coach Spencer Tamblyn coached both of them as children at the Steamboat Springs Winter Sports Club. In 2016 the Pilot reported that riders at that level spent their winters elsewhere to train on bigger pipes. Ingle describes the main purpose of the new pipe as keeping that training at home. "I think that our ultimate goal is just to build a really nice training facility for our local athletes and for the Steamboat Springs Winter Sports Club and provide a high-level venue," he told the Pilot.
He also mentioned FIS World Cup events or Shaun White's Snow League as options for later. Neither is scheduled. Ingle compares the pipe to those at Copper Mountain, Aspen's Buttermilk and Mammoth. In 2016, resort leaders said Steamboat would leave the biggest features to other resorts. The rebuilt Bashor pipe is designed to come close to what those resorts build while using about half the snow it used to.
Base-area construction is changing more of the mountain than the skyline, and the Bashor pipe is one example. The Stockman is scheduled for completion in 2030, according to FREESKIER. If you'd like to know how the work at the base could affect the part of town you care about, from Bashor Bowl to the streets around the gondola, The Labor Long Team follows these projects closely and is glad to talk them through with you. Start Your Steamboat Search with people who ride the same lifts you do.